This tutorial will provide a step by step guide on how to upgrade a ZX style machine to have Beckhoff drives and control system.
Auteur Stuga Engineer | Dernière modification 16/10/2023 par Stuga Engineer en cours de rédaction ⧼frevu-button-review-label⧽
This tutorial will provide a step by step guide on how to upgrade a ZX style machine to have Beckhoff drives and control system.
Upgrade, Beckhoff, ZX3, ZX4, Control System Upgrade_ZX_Machine_to_Beckhoff_Drives_and_Control_ZX4.JPG
Check through all parts lists and make sure that the parts that have been requested are the parts that are in the box. The picked parts should include all the consumable products that are in the BoMs (bolts, tie wraps, wires etc).
Once parts have been checked, they need to be handed to production for pre-assembly.
Ensure all information and drawing packs are available in the service job and in the relevant technical information boards on Monday.com. Link to Monday board for drawing packs here:
Before the upgrade is despatched to site, the servo system needs to be assembled and pre-wired in its enclosure.
*for detailed wiring information, please use drawing packs from Monday.com board.*
Parts
The parts should arrive on site, packed as a kit. Check the parts for any obvious signs of damage and check through to make sure you have received what was expected.
Expectations
Before starting any works, check in with the customer and make sure that all parties are aware of the scope of the work being undertaken. It is good to set expectations at this point, to keep clarity between you and the customer.
Starting the Job
Check machine condition and get pictures before starting any work. It may be useful to run the machine to check any inherent issues before the upgrade begins. After works have been started, it will not be possible to come back to this stage.
Touchscreens
Cabling
Refer to drawings