R0015286B Bench Assemble X axis Energy Chain

Auteur avatarGareth Green | Dernière modification 16/11/2023 par Stuga Engineer en cours de rédaction

Introduction

Tools Required


Small flat screwdriver

Identification markers


Parts Required


A0001112 Energy Chain Separator: 2500 Chain x 20

A0001113 Energy Chain: Series 2500.03 55mm Bend Radius x 4.2 meter

A0001114 Energy Chain Bracket Set: 24/2500 Plastic, Pivoting x 1

E0000439 Connector Brad Harrison M8 3 pole 10 m lead pvc x 2

E0001237 Pre Made Cable :Beckoff Extension AM8032 9.0m x 1

Étape 1 - Count links

Total links of for A0001113 Energy Chain is 95


Double check correct quantity



Étape 2 - Assemble links and reverse 2 off

1 Assemble 93 links together , ensure all links are orientated the same way .


2 Identify the female end of the assembled links


3 Fit 2 more links of A0001113, but fit in a reversed orientation


Étape 3 - Attach mounting brackets

Attach mounting brackets A0001114


1 Attach male bracket to reversed links and orientated as shown, This end will be identified as A


2 Attach female bracket to opposite end orientated as shown. This end will be identified as B


Étape 4 - Fit separators

1 Open all links of trunking using a small flat screwdriver to release


2 Fit A0001112 Energy Chain Separator to the following positions

Start from end A , fit 2 separators to first reversed link.


3 Counting from the first separators fitted, fit additional separators to every tenth link


4 This is correct. There will be 4 links with no separator between last fitted separators and mounting bracket

Étape 5 - Fit E0000439 Cables

Add identification markers to 2 off E0000439 cables

X291

X294


Fit cables to energy chain in section 1 as shown. Female Plugs should exit energy chain at End A . Leave 1 meter of cable to exit from plug end


Étape 6 - Fit E0001237 servo cable

Use Cable E0001237 Pre Made Cable :Beckoff Extension AM8032 9.0m x 1 and identify as 'SXA'

Fit to section 2 and leave Female plug and 0.5meter of cable to exit energy chain at the male bracket / reversed link end


Étape 7 - Fit air pipes

Cut 3 0ff lengths of 6mm x 4mm black air pipe at 9 meters

Add identification as follows

2419

1311

1319


Fit to section 3 and leave 1 meter of pipe exiting the energy chain at the male bracket / reversed link end