Access for machinery is limited at the Saje factory.
The machine will be delivered in the following modules, that should be unloaded from the lorry in this order
Machining centre base module (1.8 x 2.2m)
Machining centre outer guard 2 off (2.0 x 1.5m)
Infeed module (2.4 x 7.5m)
Conveyor modules (4.5 x 0.5m, 2.5 x 0.5m)
Pièces et outils
Pièces et outils
[[Item:|]] A fatal error occurred in the #info parser function
Utiliser des chaussures de protection
Porter des vêtements de protection
Utiliser un casque protecteur
Étape 1 - Remove the Soenen Machine
Wed / Thur before unloading, remove the Soenen machine, leaving the large outfeed conveyor tables
The Brackets on the outfeed tables will be used for the Stuga conveyors
Étape 2 - Prepare the floor
The datum points for loading have already been marked on the floor.
Using these datum points, mark the position of the remainder of the floor pads
...
Étape 3 - Triangulation for Infeed Pads
Pictures show triangulation distances.
Étape 4 - Odd pad
Additional pad needed on infeed "unwrapping" table
Étape 5 - Prepare the Machine Pads / Piles
Friday:
...Using shuttering in the pad holes will enable the height of the pad to be increased to correct the "run off" of the floor.
Pad size 300mm x 300mm (or similar)
Pad Depth 300-500mm
Use shuttering or large diameter soil pipe
Find the highest point, string a level agcross to the other pads
Fill shuttering with quick set cement to +/- 15mm of level
...The machining table has levelling feet, but the run off of the current cow shed floor may prove challenging for the range of the levelling. Using the shuttering to create taller plies will solve this problem easily and inexpensively
Étape 6 - Prepare unloading bogeys
Window loading bogeys (3 off) to be prepared on a rigid base to allow one end of machine infeed frame to rest on them
The forklift will lift and push from the other end
Étape 7 - Clear the inside area
Including the chop saw table
Leaving a clear route for the 2.4m x 7.5m table to roll in
Étape 8 - Clear Outside Unloading Area
The full width of this route will need to be cleared
Étape 9 - Imporvements to step into building
If possible, improve the access pathway.
Potentially find a ramp system for the step into the unit
Étape 10 - Lorry to reverse along LHS of building
Monday:
Lorry to reverse along left side of building (when viewed from front)
This allow easy unloading access for forklift to unload to ground, and align components with door
Étape 11 - Machining Centre
The machining centre
Étape 12 - Machining Centre Guard
The guar is a clam shell design that encases the machine in 2 pars from front and rear
Commentaires
ennone0Draft
×
Erreur de saisie dans le nom du tutoriel
Vous avez entré un nom de page invalide, avec un ou plusieurs caractères suivants :
< > @ ~ : * € £ ` + = / \ | [ ] { } ; ? #
Connexion
Pas encore enregistré ? Créez un compte pour profiter de toutes les fonctionnalités du service !