Saje uPVC Unloading Process

Auteur avatarGareth Green | Dernière modification 22/02/2023 par Gareth Green en cours de rédaction

Pas encore d'image

Introduction

Access for machinery is limited at the Saje factory.

The machine will be delivered in the following modules, that should be unloaded from the lorry in this order

  1. Machining centre base module (1.8 x 2.2m)
  2. Machining centre outer guard 2 off (2.0 x 1.5m)
  3. Infeed module (2.4 x 7.5m)
  4. Conveyor modules (4.5 x 0.5m, 2.5 x 0.5m)

Étape 1 - Remove the Soenen Machine

Wed / Thur before unloading, remove the Soenen machine, leaving the large outfeed conveyor tables

The Brackets on the outfeed tables will be used for the Stuga conveyors


Étape 2 - Prepare the floor

The datum points for loading have already been marked on the floor.

Using these datum points, mark the position of the remainder of the floor pads

...

Étape 3 - Triangulation for Infeed Pads


Étape 4 - Prepare the Machine Pads / Piles

...Using shuttering in the pad holes will enable the height of the pad to be increased to correct the "run off" of the floor.
  • Pad size 300mm x 300mm (or similar)
  • Pad Depth 300-500mm
  • Use shuttering or large diameter soil pipe
  • Find the highest point, string a level agcross tot he other pads

Étape 5 - Prepare unloading bogeys

Window loading bogeys (3 off) to be prepared on a rigid base to allow one end of machine infeed frame to rest on them

The forklift will lift and push from the other end



Étape 6 - Clear the inside area

Including the chop saw table

Leaving a clear route for the 2.4m x 7.5m table to roll in


Étape 7 - Unload and