Flowline 6 to 6o5m Extension

Auteur avatarGareth Green | Dernière modification 30/03/2022 par Gareth Green en cours de rédaction

Introduction

This procedure describes how to upgrade a flowline to increase the standard capacity from 6.0m to 6.5m.

The procedure involves extending the machining centre outfeed travel and saw infeed travel base to 6.0m to cope with a longer rail on each side. These are generally supplied as a new part.

Other ancillary parts that will need extending

  • Cables
  • Energy Chains

Étape 1 - Remove Guarding/Extraction

Isolate power to extraction and then disconnect the cable from extraction motor. Remove floor bolt nuts from the extraction unit feet, and separate the ducting so that the unit can be moved.


Once moved, disconnect all guarding to the far end of multi outfeed and saw infeed (pictured).


Detach Outfeed beam sensor with the bracket so that the rear guarding support box section can be removed.



Étape 2 - Removing carriages and replacing Journals

Remove both X and SX rear limit stops blocks, then disconnect all energy chain cables and air pipes at the carriage end.

Unclip the energy chain and remove both carriages from the axis.


On a bench, remove Gearbox/motor assembly's and replace the pinion gears (add a small amount of Loctite on grubscrew when re-tightening).


Now remove all x6 journals and x6 covers from carriage and disregard.

Then Fit:


x3 Concentric Journals - These must be fitted on the TEETH SIDE of the Hepco rail.

x3 Eccentric Journals - Fit on the opposite side and LEAVE LOOSE for now.


Leave the x6 Journal covers off for now.



Étape 3 - Remove Hepco rails

Detach both Hepco rails by removing the 6mm caphead bolts (pictured).


Once rails are removed, they can be separated into shorter lengths by knocking out the dowel pins towards the centre sections.



Étape 4 - Prepare Hepco support base surface

Clean and remove any dirt/grease/imperfections on the box section ready the the new rails.


If any of the tapped holes are compromised, re-tap 6mm.



Étape 5 - Drilling Extension Pieces

Offer extension piece (box section) up to existing axis beam and clamp on using large G clamps and fixing angle **(*pic required) **


Mark holes in both pieces then drill/ tap 6mm.



Étape 6 - Fit Extensions

Fit angle bracket to extension box sections using 6mm capheads....and locknuts where accessible for extra security (pic).


Do not fit to mainframe yet....only use G clamps until Hepco rail is attached.



Étape 7 - Fit 6.5m Hepco Rail

Fit new Hepco rail using 6mm capheads whilst extension piece is clamped onto frame (Pic).


Each new Hepco rail will require pinning together, making sure the joints are as seamless as possible to allow gripper/pusher carriages to pass over freely.


Once rails are fitted to main frames, new holes can be marked/drilled/tapped 6mm on the extension pieces and secured.




Étape 8 - Final Bracket Fix

Now the last fixes between the angle and main frames can be drilled/tapped and secured.



Étape 9 - Extend Cables and pipes

All Energy chain cable and pipes, as well as the energy chain itself, will need to be 500mm longer.


If theres enough slack on current cables(and are in good condition), then extend and re-route. All other cables and air pipes will need replacing.


The energy chain itself will require extra links fitted (500mm).


Other cables that will need to be extended/or replaced:

Extraction power cable.

SX axis datum switch cable.

Outfeed beam cable.


Étape 10 - Moving Datum bracket



Étape 11 - Moving Rear guard mounting bracket



Étape 12 - Fit extra Transfer support block



Étape 13 - Re-fit Guarding



Étape 14 - Fit profile support plate



Étape 15 - Extend Extraction



Étape 16 - Set up Parametres