R0015346 Conveyor blower system

Auteur avatarGareth Green | Dernière modification 5/06/2024 par Gareth Green en cours de rédaction

Introduction

Tools Required


Standard hex key set

Pipe cutters

Pipe identification numbers


Parts Required


P0000046 Fitting: 'Y' Adaptor 6mm x 1

P0000053 6mm T (P16) x 1

P0000160 Fitting: Flow Controller In Line 6mm x 1


Étape 1 - Unless otherwise stated

Use Loctite 243 on all fasteners

Use Loctite 572 on all threaded pneumatic connection

Pen mark all fasteners to show finalised



Étape 2 - Connect Drive roller blower

Use 6 x 4 mm black air pipe .


Use identifications of 2139


Connect blower elbow to in line flow regulator


Connect flow regulator to 6mm Y connector

Correct photo required please


Étape 3 - 6mm Y connector

6x4mm black air pipe .


From 6mm Y connector


1 pipe to run to saw connection . Leave trailing pipe 2 meters long with identification


1 pipe to run along indicated side of conveyor to feed top blowers

Correct photo required please


Étape 4 - 6mm Tee connection

Split feed pipe with 6mm Tee connector at upper bracket position


fit inline flow regulator before 6mm tee connector


run one feed pipe direct to blower



Étape 5 - Last blower feed

Attach feed pipe to tie bases and feed last blower elbow



Étape 6 - Pneumatics test

Connect air feed to trailing 6mm pipe


Check all flow regulators are installed in the correct orientation


When flow regulators are fully closed, air should be stopped .


If air can only be regulated to a small flow, regulator is installed in the wrong orientation


Commentaires

Draft