This guide is to be used for all of the electrical connections when installing a ZX5 machine.
Auteur Stuga Engineer | Dernière modification 5/12/2023 par Stuga Engineer en cours de rédaction ⧼frevu-button-review-label⧽
This guide is to be used for all of the electrical connections when installing a ZX5 machine.
ZX5, Electrical, Installation Installation_Guide_-_ZX5_Electrical_electrical_connection.JPG
Module A is where the factory mains supply comes into the machine. A cable is supplied on the screen and this needs to be terminated appropriately according the termination method given in the customer factory.
There will be 3 cables coming from the Machining Centre module that need to be connected to Module A. The cables are as follows:
There will also be a HDMI cable coiled up on Module A that needs to be run to Module F electrical cabinet. The HDMI cable needs to be run through the Machining Centre, down the Transfer basket tray and into the bottom brush of the Module F electrical cabinet. The HDMI cable then plugs into the HDMI port in the front end PC.
An earth bond will be loose that needs connecting to the Machining Centre frame. The connecting point will have an 'Earth' sticker as reference.
Module B is where the network from the factory comes into the machine. A network cable with an RJ45 plug will need to be supplied by the customer and this will need to be connected into the top port of the yellow ethernet switch inside the Module B electrical cabinet.
Module B cabinet will be completely wire but it will have a number of cables coming out of the back that need to be connected to external devices. The connection that need to be made are as follows:
Termination checks
Door unlock
Estop check