Upgrade ZX Machine to Beckhoff Drives and Control

Auteur avatarStuga Engineer | Dernière modification 16/10/2023 par Stuga Engineer en cours de rédaction

Introduction

The ZX3 and ZX4 machines that have control systems that pre-date the Beckhoff hardware now have an upgrade available. The upgrade will bring up-to-date hardware to the machines control system and drives. The control system and drives will be changed to Beckhoff. TwinCAT 3 PLC and AX8000 series drives.
Attention
Consulter le manuel d'instructions
Utiliser des chaussures de protection
Pour l'entretien, débranchez l'appareil du secteur
Avertissement générique
Haute Tension

Étape 1 - Preparation (Base)

Check through all parts lists and make sure that the parts that have been requested are the parts that are in the box. The picked parts should include all the consumable products that are in the BoMs (bolts, tie wraps, wires etc).


Once parts have been checked, they need to be handed to production for pre-assembly.


Ensure all information and drawing packs are available in the service job and in the relevant technical information boards on Monday.com. Link to Monday board for drawing packs here:


https://stugaltd.monday.com/boards/3338864598



Étape 2 - First Fix Servo Cabinet

Before the upgrade is despatched to site, the servo system needs to be assembled and pre-wired in its enclosure.


  • Drill off Fan detail in right hand side of cabinet. A 114mm hole saw and arbor has been purchased for this.
  • Drill and fit 4 adjustable feet in the bottom of the cabinet. 4 extra nuts will be in the kit. The height of the feet does not need to be set at this stage.
  • Drill off all servo drives. For ZX3 machines, the rack will be as follows: AX8640-AX8118-AX8206-AX8206 and for a ZX4 the will be: AX8640-AX8118-AX8206-AX8206-AX8206 (the extra drive is for the V and W axes).
  • Pre-wire the rack (inc STO links) and the cabinet fan with the cable provided in the kit. leave the spare coil of cable in the cabinet ready for running on-site.
  • Plug in the 2x15m green etherCAT cables.
  • The enclosure bottom plate is left off to allow the cable entry on site.

*for detailed wiring information, please use drawing packs from Monday.com board.*

Étape 3 - Preperation (On-Site)

Étape 4 - Remove Components - MH (Electrical)

Étape 5 - Remove Components - Saw (Electrical)

Étape 6 - Remove Components - Saw Infeed (Electrical

Étape 7 - Remove Components - Field Components

Touchscreens

Cabling

Étape 8 - Fit Parts - MH (Electrical)

Étape 9 - Fit Parts - Saw (Electrical)

Étape 10 - Fit Parts - Transfer (Electrical)

Étape 11 - Fit Servo Cabinet

Étape 12 - Wiring Cabinets

Refer to drawings

Étape 13 - Run Machine Cabling

Étape 14 - Upgrade Console - MH

Étape 15 - Upgrade Console - Saw

Étape 16 - Terminate Machine Wiring

Étape 17 - Tidying and Checks

Commentaires

Draft