The Beckhoff system provides a system for upgrading to TC3 from a TC2 project. This tutorial goes through the steps required to ensure the links and setup of the original TC2 project are copied through to TC3.
Étape 1 - Get connected to the Camera PC of the machine to be updated
You will need to get a backup of the TC2 project from this machine, and use it to set up all the correct IO links in the TC3 project
Étape 2 - Get a backup of the original TSM file
Dial in to Camera PC
Open System manager
File->Save As
Rename it to [build number].[todays date]
Copy to c:\twinCAT\stuga\ on the "New" camera PC
Étape 3 - Get copy of current PLC and Reset project
Open the PLC Control program on the camera PC
Note the version of software currently running (.pro)
Find the .pro file in c:\TwinCAT\Stuga\
Copy to c:\twinCAT\stuga\ on the "New" camera PC
Also copy the latest PLC Reset project
Étape 4 - Convert the TC2 project to TC3
Open Visual Studio
Create a new TC3 project called [BuildNo] in c:\TwinCAT\Stuga\
Make sure "Create Directory..." is Unticked
Right Click on the project name and select ‘Load Project from TwinCAT 2.11 Version…’
Click Cancel on the two windows asking to convert the PLC project
Ignore or cancel any warnings about libraries (this part will be replaced later)
...Once created, you will have a copy of all the devices and boxes in the project with the correct naming.
Étape 5 - Create the clone to pull the latest tc3Multi and PLC_Reset
Create the clone in c:\TwinCAT\[BuildNo]\Source
If an error is produced after cloning, just use the "Add" function to add the clone
Étape 6 - Replace the old PLC code with the version control latest
Delete the old PLC projects
using Add existing item, add the tc3Multi then PLC_Reset projects from c:\TwinCAT\[BuildNo]\Source.
Ensure Use Original project Location is selected
Build the solution to create the instances ready for linking
Ensure the Port numbers are correct (851=tc3Multi, 852=PLC_Project)
Étape 7 - Connect to the Beckhoff Backend PC
Add a new route
Étape 8 - Update the EtherCAT Device Adaptor
Navigate to the Adaptor settings and search for the correct one on the new Beckhoff PC
...When you converted the TC2 project, it imported all the etherCAT boxes, but critically, it also imported the "EtherCAT Device". This is the hardware spec of the original Beckhoff PC, with a MAC address, etc.
You now need to change this in the project to the EtherCAT device on the new Beckhoff PC
Étape 9 - Add the IO Links
...This is a LOT easier on a dual screen PC!
...Regrettably, the upgrade will not keep all the IO links, so these need to be entered again manually
Using System Manager on the Camera PC, create new copies of all the links on all devices from the System Manager to the new project.
...A lot of the Autoflows have been modified on the EtherCAT network - eg a sensor input may have blown and the sensor has been moved to a different port. Using this method ensures you get exactly the same setup.
Étape 10 - Change the inverterGoFwd links
TC2 software used a system of inverter objects to control the spindles, saw blade and extractor. The mapping will show InverterGoFwd mapping.
These need to be changed to the correct output numbers for the outputs in question.
On an Autoflow, these are
Slice MC03B (ModuleB)
Ch0 - Y62 Spindle Inverter
Slice MC2F (module F)
Ch1 - Y97 Saw Blade
Ch 2 - Y98 Extractor
Étape 11 - Copy the Axis Links
The PLC links will be missing - reinstate them as per System Manager on old Camera PC
If The 'Link to PLC' field is not viewable on Twincat 2 project use the below guide for the correct links required:
When converting for a ZX4 machine, the V and W axis links will need to be changed
V = arrAxis[11]
W = arrAxis[12]
...This is needed because the original ZX4 number designations (7&8) overlapped those used on the SR and SY axis. This created a problem on the ZX5, because it used both a V axis and SR&SZ. Decision was made to give V and W their own axis numbers for future compatibility
Étape 14 - Add the reset link
Set a link from ibResetPLC on PLC_Reset to qbResetPLC on tc3Multi
Étape 15 - Ensure the front end has the latest software versions
Étape 16 - Update the front end parameters
In params.saw, the following parameters must be updated
controllerType=5
amsnetId= [AmsNetId of the new Beckhoff PC]
twinCAT Address=[AmsNetId of the new Beckhoff PC]
AllWasteAtStart=1
useSawForYNotch=1
Étape 17 - Update the Control Systems log
Update
Front End PC and OS
Back End PC and OS
Software versions
Commentaires
ennone0Draft
×
Erreur de saisie dans le nom du tutoriel
Vous avez entré un nom de page invalide, avec un ou plusieurs caractères suivants :
< > @ ~ : * € £ ` + = / \ | [ ] { } ; ? #
Connexion
Pas encore enregistré ? Créez un compte pour profiter de toutes les fonctionnalités du service !