R0015268 Pneumatic module Test

Auteur avatarGareth Green | Dernière modification 11/12/2023 par Gareth Green en cours de rédaction

Introduction

Tools Required


Parts Required

Étape 1 - Prepare area for testing

Ensure area is clear and free from personnel

Étape 2 - Connect mains air supply

Connect mains air supply and check for any leaks present is components natural state

Étape 3 - check home positions

Check home positions are correct in natural state


Loader wheel Y154 should be up away from roller beds in home position


Roller beds Y157 should be in the up position in home position


Blowers Y375 should be switched off in the home position

Étape 4 - Test Y154 output

On valve bank, manually fire Y154 output.


Check for air leaks when output is fired


Check regulator shows pressure when fired by increasing pressure with adjusted .Once confirmed correct operation, a djust regulator to 1 bar or 0.1 mpa

Étape 5 - Test Y157 Output

On valve bank, manually fire valve Y157 roller lift output


All rollers should drop down into position. When fired, check there are no air leaks present in the active position

Étape 6 - Test Y375 Output

Manually fire Y357 output Check each blowers flow regulator can adjust flow rate when turned . Once confirmed , fully close flow regulator and wind out 2 turns

Étape 7 - Disconnect air supply