Introduction

Tools required


Parts Required

Étape 1 - Health and Safety

In this process pneumatic outputs will be tested in a non emergency stop environment


Ensure safe working practice is followed


  • Ensure Machine test area is clear from personnel and all staff are aware of testing procedure commencing
  • Ensure all Air connection lines are connected
  • Ensure all walkways are not impeded by trailing pipes/leads
  • Ensure all mechanical assemblies are at a sufficient stage for testing



Étape 2 - Check all connections are made

  • Check all valve bank ports are either connected or blanked off
  • Check all mains feed pipes are connected or isolated
  • Check all regulators are regulated to minimum setting
  • Check all air flow control valves on cylinders and blow lines are set to mid range adjustment

Étape 3 - Connect air feed

Connect air feed to mains 12mm feed pipe using pcl coupling and 12mmm push fit adapter

Étape 4 - check for air leaks

Investigate any air leaks and resolve

Étape 5 - Test valve bank outputs

Each valve on the Valve bank can be manually overridden to activate the output.

When each valve is individually

Étape 6 -

Étape 7 -

Étape 8 -

Étape 9 -

Étape 10 -

Étape 11 -