Key Steps for mechanical installation of ZX5
Auteur Gareth Green | Dernière modification 13/12/2023 par Gareth Green en cours de rédaction ⧼frevu-button-review-label⧽
Key Steps for mechanical installation of ZX5
ZX5_Installation_Procedure_2023_Screenshot_2023-04-21_093450.png
Key data for installation of ZX5
Identify if either saw infeed or multi head outfeed is the logical frame to place first .
Consider access to machine when installing 1st frame
Consider handing of machine
Both frames will be initially levelled in the same way, and then fine tuned once multi head or saw is installed
Y axis levelling
X axis is initially set up using the hepco rail as a register. Once additional units are installed and levelled , this x axis setting will be re checked and adjusted if required
Points A and B should be level with each other.
Adjust 2nd frame up or down on all frame bolts to achieve this
Add remaining 7 transfer beams to two installed frames and fix in position on support arms
It is crucial to set the squareness of the transfer table by adjusting the infeed/ outfeed tables.
1 The squareness can be checked by using a tape rule to make corner measurements at the points indicated
2 Second frame can be moved in the directions shown to adjust the corner measurements to make them both the same
Machining center is aligned to the out feed using the following
Grip pin setting jig
Laser level
2 meter straight edge
X axis position is determined by hepco rail travel at full extent and center clamp bar within machining center. The gap here should be approximately 10mm. However on installation position of this axis may be marked on the machine to be installed from previous installation
Y axis position is determined by the grip pin jig and the machining center backfence rollers
Height is determined by the datum horizontal rollers in the machining center and the blue rollers on the outfeed table
Place laser level in the rear datum roller section of the machining center
Position gripper carriage as close to the laser level as possible
Mark a horizontal line of the carriage plate as a height datum
Move the carriage to above the next section of frame feet and adjust the pair of jacking bolts to adjust line to be on laser level mark
Repeat this step above every pair of frame legs where jacking bolts are
These steps will ensure the outfeed is now set on a dead flat plain
4. Use the pin jig to adjust the position of the machining center to allow the gripper pins to align with the jig at all points along the back fence rollers. hepco beam should also be moved from in to the out position also to double check this jig setting
5. Use laser against machining center rollers to cast a laser line along the outfeed. Pull the gripper as close as possible to the laser, and mark a vertical line on the gripper where the laser dot falls.
Move the gripper to the end of the hepco rail and check if the laser stop still aligns on the vertical line previously marked . If it doesn't , grip pin alignment will need re checking as it is crucial that both of these areas are correct
6 final height adjustment is set by using a 2 meter straight edge through the machining center rollers to the first set of rollers on the outfeed table. Machining center can be adjusted up or down to bring these rollers all onto the same height plain
Saw back fence and saw infeed back fence are used for y axis alignment . Saw back fence should be slightly in front of saw infeed back fence. Around 1mm
2. X axis alignment
Frames should be marked to show measurement between frames to set this position . if not the defining factor is the gripper must not hit eject clamps when at full travel on x axis
en none 0 Draft
Vous avez entré un nom de page invalide, avec un ou plusieurs caractères suivants :
< > @ ~ : * € £ ` + = / \ | [ ] { } ; ? #