Method for levelling bare frames for modules A,C and F for ZX5/3 Preparing frame for production
Auteur Gareth Green | Dernière modification 3/04/2024 par Gareth Green en cours de rédaction ⧼frevu-button-review-label⧽
Method for levelling bare frames for modules A,C and F for ZX5/3 Preparing frame for production
ZX5_module_A-C-E_Frame_levelling_Screenshot_2023-03-13_092825.png
Procedure to prepare frame for build sequence
tasks to include
Parts Required
Tap all holes to remove debris from coating process
Ensure all holes cleaned after tapping with compressed air
Fit 10 off m16 x 1.5 x 120 set bolts with standard m16 x 1.5mm nut and copper slip to lubricate lock nut and thread into frame.
Use a pallet truck to lift frame.
Wind through M16 bolts until approximately 20mm protrusion from below base of foot
Locate each bolts into black nylon levelling pad
1 Attach levelling jigs to 5 points across frame
2 Use level on jig to indicate current state of level
3 Check across all 5 points to identify where to lift frame to achieve level
4 Lift frame by jacking bolts to achieve level on level jigs
Bolts should be increased uniformly until close to desired levelling point.
For example, 1 turn clockwise on bolt 1,then 2,3,4 and 5
then repeat5 Adjust level on Y axis until all level points are correct.
1 Place one parallel at point 1 and 1 parallel at point 2. Span these with a 2mtr straight edge and use engineers level on top of straight edge to show current level
2 Repeat this between point 2 and 3 , then 3 and 4 and finally 4 and 5. This will highlight the movement required to level frame
3 Use the same method as the Y axis
4 achieve all points 1-5 level , any discrepancy should be reported to the Supervisor
en none 0 Draft