Key Steps for mechanical installation of ZX5
Auteur Gareth Green | Dernière modification 13/12/2023 par Gareth Green en cours de rédaction ⧼frevu-button-review-label⧽
Key Steps for mechanical installation of ZX5
ZX5_Installation_Procedure_2023_Screenshot_2023-12-05_141423.png
Key data for installation of ZX5
Dokit to generate consistency of installation
Quality checks for installation
In each step if applicable, Manufacturing links have been included to aid the installation progress for correct understanding of assembly process to achieve desired results
Please use the links if any adjustments have to be made on site, as critical measurements and setting details will be provided within the build data
Please ensure any quality/ discrepancies are correctly reported if encountered
Identify if either saw infeed or multi head outfeed is the logical frame to place first .
Consider access to machine when installing 1st frame
Consider handing of machine
Position first frame identified to be first and set parallel to installation area
Take into consideration walkways, access one machine is installed and service connections
It is vital the support arm is utilized at this point to allow correct adjustment of position 1 and 2 support arms
Use the adjustment in the foot to correctly level arms 1 and 2
Both frames will be initially levelled in the same way, and then fine tuned once multi head or saw is installed
Y axis levelling
Once the previous step has been performed, reference brackets should be checked to confirm factory setting has been achieved
The levelling brackets indicated should match the level of the support arms
Discrepancy should be immediately reported
X axis is initially set up using the carriage plate as a register. Once additional units are installed and levelled , this x axis setting will be re checked and adjusted if required
Please note photo of level is taken from production stage. It is to give reference of the part to be used to to set X axis level. Position level at available point on assembled carriage plate
R0015028D ZX5 Hepco Beam Alignment Module C
R0015028D ZX5 Hepco Beam Alignment Module C part 2
Points A and B should be level with each other.
Adjust 2nd frame up or down on all frame bolts to achieve this
Take care not to effect previous level settings when adjusting height
It is crucial to set the squareness of the transfer table by adjusting the infeed/ outfeed tables.
1 The squareness can be checked by using a tape rule to make corner measurements at the points indicated
2 Second frame can be moved in the directions shown to adjust the corner measurements to make them both the same
Tolerance -+ 3mm
R0015291 Install Transfer Beams To Module C and E
Add remaining 7 transfer beams to two installed frames and fix in position on support arms
Once all transfer beams are installed, it is vital to check that the top faces or the transfer beams are all aligned to each other and provide a flat table for correct profile transfer
Use 2 meter straight edge to inspect top faces in relation to each other