  • 1 Cut 8 off pieces of black air pipe @ 230mm and fit as shown to all connection boxes, noting pipe routing 2 Cut 8 off pieces of black 6mm air pipe @ 190mm and fit as shown to all connection boxes  +
  • 1 Install 300hz cable from single slide spindle as shown (4 off) 2 Install 300hz cable from double slide spindle as shown (4 off)  +
  • 1 Prepare 8 off P0001091 bulkheads with a1 Prepare 8 off P0001091 bulkheads with a piece of 32mm long 6mm black pipe added and one nut removed 2 Push pipe into cylinder fitting with nuts loose as shown 3 Apply force on fitting towards cylinder and run indicated nut to face to ensure no strain is added to fitting when tightening 4 Spin indicated nut to the connection box face and then tighten nuts connection box face and then tighten nuts  +
  • 1 Cut 4 off pieces of 6mm black airpipe @ 245mm and install in double slide connection boxes as shown, noting pipe routing 2 Cut 4 off pieces of 6mm black airpipe @ 205mm and install in double slide connection boxes as shown, noting pipe routing  +
  • 1 Double valve connections Use compact 6mm tee P0001023 and connect two valves together as picture Lay feed pipe over top and mark length, cut and connect 2 Single valve connections Lay feed pipe over valve fitting, mark and cut then connect  +
  • 1 Fit 4 off P0000456 m5 -4mm straight fittings to double plunge connection boxes ( 2 valve boxes) 2 Fit 2 off Poooo456 m5-4mm straight fittings to single plunge connection boxes (1 valve boxes) and 2 off M5 x5 button heads as blanks  +
  • 1 Fit P0001091 bulkhead connector to all s1 Fit P0001091 bulkhead connector to all spindle boxes at position shown, ensuring orientation of bulkhead is the same 2 Cut 8 pieces of black 6mm air pipe @230mm long and fit as show 3 Add P0001091 bulkhead to double slide connection boxes only as shown
    lide connection boxes only as shown <br/>  +
  • 1 Loom with spiral wrap as shown sensors f1 Loom with spiral wrap as shown sensors from double plunge assembly 2 Loom with spiral wrap as shown sensors from single plunge assembly
    ...Ensure sensors are loomed to enable loom to sit flat on spindle base and have minimal slack or exposed loom

    to sit flat on spindle base and have minimal slack or exposed loom</div> </div><br/>  +
  • 1 Use 4mm black air pipe to connect lower valve in all connection boxes as shown 2 On double valve boxes overlay second set of pipes to connect exhausts of top valve  +
  • 4 off 1 Mount pre assembled valve into 4 off 1 Mount pre assembled valve into spindle connection boxes to the left of the single slide spindle assembly (as viewed from rear) 2 Use 3 off M3 x 12 pan heads to secure valve to connection box as shown 3 Before tightening, add 4 off D0010807 upstand collars to define position of valve mounting 4 Finalise fixingition of valve mounting 4 Finalise fixing  +
  • 4 off 1 Mount double stack of valves int4 off 1 Mount double stack of valves into spindle boxes to the left of the double plunge spindle assemblies. (as viewed from rear) 2 Use 3 off M3 x 25 pan heads to secure valve to connection box as shown 3 Before tightening, add 4 off D0010807 upstand collars to define position of valve mounting 4 Finalise fixingition of valve mounting 4 Finalise fixing  +
  • Fit 2 off P0001093 stem elbows as shown then connect 4mm airpipes over length as shown to either connection ( these will be identified and tidied later on) Repeat on remaining 3 double plunge connection boxes <br/>  +
  • Fit remaining p0001091 bulkhead to double slide connection boxes as shown  +
  • It is vital that no air pipes are kinked on installation . Ensure all pipes are checked for correct running . Example attached of kinked pipe  +
  • Please ensure all looms created and run are identical on each spindle head and copy examples shown . Looms must be kept to minimal size to protect from debris during operation  +
  • Use Loctite 243 on all fasteners Pen mark all fasteners to show finalised  +