  • All bolts to have Loctite 243 adhesive applied unless otherwise stated All Threaded Pneumatic connections to have Loctite 570 applied All bolts to be pen marked once adhesive applied and correct tension added  +
  • Connect 21b To FB01B out port to FB02B in port , routing as shown  +
  • Connect 22b To FB02B out port to FB03B in port , routing as shown  +
  • Connect 23b To FB03B out port to FB04B in port , routing as shown  +
  • Connect X120 VY datum cable from wiring loom to sensor shown . Leave trailing ready for looming  +
  • Connect X247 from loom box onto V safe sensor and route as shown to FB01B  +
  • Connect cable 20b to in port on Fb01B and route as shown  +
  • Retrieve 24B cable which exits the rotary head energy chain and loom to box FB04B out port  +
  • Retrieve X488 and X56 from rotary ring loom and route around trunking to EC04B  +
  • Retrieve X50 from energy chain rear and route as shown, exiting at FB04B  +
  • Route X111 and X112 reed switches from loom box and route as shown Reed switches to exit same side as cylinders for V notch clamps Ensure minimal cable length is left at FB01B connection end Coil reed switches onto cylinder for temporary measure  +
  • Route X53 cable as shown, to EC04B  +
  • Route X63 reed switch to the route shown, leaving minimal cable for termination at FB04B end  +
  • Route fitted reed switches X459 and X460 to FB01B Ensure spiral wrap is used and routed as shown  +
  • Route power cables from ring and exit as shown for Z105 and later Z104 will have green power cable instead of grey, and single earth cable , route same as above  +
  • Route reed switch X65 as shown. Finish atRoute reed switch X65 as shown. Finish at FB04B Ensure maximum length is left for routing to cylinder at a later point
    ...L-R machines Require extension cable to allow correct routing. See electrical team for additional cable. Cable join/plug must be left in vertical trunking for ease of access

    ble join/plug must be left in vertical trunking for ease of access</div> </div><br/>  +
  • Route reed switches X59 and X61 from FB04B to exit at point shown of trunking Ensure minimal length of cable is left at FB04B termination end  +